INCLUDE Progress Dashboard
Loading workbook data...
GIZ INCLUDE

Overview of Progress

Implementation of the Innovation Lab Process and 12 respective Process Lines in Bangladesh under the Innovations for Climate-smart Urban Development (INCLUDE) Project.

Municipalities 4 Sirajganj, Gaibandha, Chapainawabganj, Charghat
Innovation Lines 12 Climate, water, waste, heat, health, agriculture
Milestones 42 13 submitted, 3 in progress, 26 pending
Overall Progress 32%

Project Background

The Innovations for Climate-smart Urban Development (INCLUDE) project, funded by BMZ and implemented with support from GIZ, promotes locally led climate-smart urban development in Bangladesh. The assignment supports four municipalities: Sirajganj, Gaibandha, Chapainawabganj, and Charghat. Through the Innovation Lab Process, the project helps selected local ideas move from concept refinement into practical implementation. The current assignment focuses on phases 5 and 6 of that process: refinement, development, validation, implementation, and integration of small-scale measures into municipal systems. Twelve innovation lines are being supported across themes such as urban heat resilience, water security, drainage, waste management, health risk reduction, climate-resilient agriculture, digital tools, and inclusive community engagement. The work also emphasizes participation of marginalized and climate-vulnerable groups, including women, youth, elderly people, and people with disabilities. Dorsch Impact and NIRAS support GIZ, LGED, municipalities, idea providers, developer teams, and local partners through coordination, technical inputs, capacity development, partnership building, knowledge management, procurement preparation, progress monitoring, and reporting. This dashboard consolidates project status, milestone progress, idea-wise implementation updates, quarterly progress summaries, deliverables, and expert input planning into one operational view.

Overall Progress

Work package and milestone status

Milestone Status

Submitted 13 In progress 3 Pending 26
Month-wise Total Progress 32%

Work Package-wise Progress

Work PackageTotalSubmittedIn ProgressPendingProgress
WP1 Assignment Management and Coordination1041548%

Milestone Register

Showing all milestones

IDMilestoneDeliveryStatusProgressRemarks
1.1Inception ReportEnd of month 3In progress75%Submitted 31 January 2026
Idea-wise Implementation Progress

Innovation line updates by municipality

Showing all innovation lines

MunicipalityIdeaStatus
SirajganjUrban heat resilienceWorkbook-driven status summary
Quarter-wise Progress

Summarized narrative from Quarterly Progress Reports

QPR1 Summary

Jan-Mar 2026

Completed Activities

  • Mobilized lead experts, assignment management, communication/PR expert, and municipal coordinators.
  • Conducted stakeholder consultation workshops in Sirajganj, Gaibandha, Chapainawabganj, and Charghat.
  • Held bilateral meetings with idea providers to understand technical logic, readiness, costing, and governance.
  • Established Microsoft Teams-based knowledge management systems for internal and GIZ collaboration.
  • Prepared idea-specific stakeholder maps, preliminary site longlists, partnership scoping, and needs analysis.

Submitted Deliverables

  • Inception Report package, including management, communication, process, third-party, engagement, and capacity concepts.
  • Annual Planning Workshop Report for 2026.

Next Quarter Priorities

  • Partnership development and initial partnership meetings.
  • Needs analysis, design refinement, and idea-specific design workshops.
  • Procurement support, survey requirements, technical specifications, and tendering documents.
Expert Inputs

Actual/current versus planned expert resources

Actual/current values are calculated through the current month.

Lead Experts
Short-term Experts

Expert Detail

Showing all experts

CodeName / DesignationGroupAllocatedActual/CurrentPlanned/FutureBalance
KEWorkbook-driven expert rowLead0000